Industry: Transport
Rehabilitation of the Kampala – Malaba Meter Gauge Railway (MGR) Line (234 Km), Including Jinja Pier Line (3.2 Km), Jinja Pier Yard (0.5 Km), Crossing Lines (8 Km), and Naigombwa Swamp Drainage Improvement (Box Culverts)
Kampala, Uganda

Client
Uganda Railways Corporation
Funder
Government of Uganda
Value of services
Start / End Dates
September 2022 - August 2023
The project involved renewal of the meter gauge track, including re-laying of rails, replacing damaged ties, and adding and compacting ballast. The project also involved the inspection and rehabilitation of critical bridges, culverts, and strengthening of embankments in selected sections to enhance structural integrity and safety.
Planning, feasibility, conceptual design
Design
Construction
Operations and maintenance
Decommissioning